BUREAU OF CONSTRUCTION & MATERIALS


Proposal Information

Letting Date:  07/22/2020

Questions or Comments may be sent to:
Lee Alvarado Lee.Alvarado@ks.gov
(785) 296-3576

 

 

KDOT realizes that the February 2020 wage rate determinations contain some wages that are not consistent with others. To that end, we have been communicating with the US Department of Labor (DOL) since February in an effort to convince DOL to rescind or revise the February 2020 wage rate determinations. The Secretary was able to negotiate a reprieve for the February and March lettings, but DOL denied a third request. We are working with the KCA and others to determine the next steps to discuss with DOL regarding wage rates that are out of line with others. Until further notice, the February 2020 wage rate determinations must be followed.

The Kansas Department of Transportation July 22, 2020 letting WILL remain as scheduled with the following procedural change to enable the reading of bids in a manner that accommodates the public building restrictions due to the COVID-19 emergency.

The KDOT July 22, 2020 bid letting will be conducted by audio broadcast ONLY at 3:00 pm on Wednesday, July 22, 2020 through a conference call. For the conference call dial 866-620-7326, and enter conference code 5895748207. The letting will be conducted remotely and KDOT has tested the process, but if there are any glitches while conducting the bid letting remotely we will be in contact and keep you updated. Thanks.

The Proposal Form consists of the following documents: the Project Electronic Bidding System (EBSX) file on Bid Express’ website (which includes DOT Form 202, required contract provisions and the unit prices list), special provision list, project special provisions, special provisions, standard specifications, plans, exploratory work documents, any additional contract information, all questions and answers posted on the Bid Express website, and any addendums or amendments the Secretary provides for the Project. Contractors interested in bidding as a prime Contractor and potential subcontractors and suppliers shall acquire these documents using the links provided in the Project information below for the Particular project of interest. Subcontractors, suppliers, and other interested entities may use the Non-Bidding EBSX file link below to view a pdf copy of the Project EBSX file rather than downloading the EBSX file that Contractors use to prepare their proposal.

The Proposal Form becomes the Bidder’s Proposal after the Bidder completes the EBSX file (which includes DOT Form No. 202, the Unit Prices List, and applicable required contract provisions), electronically signs the Proposal where required on DOT Form No. 202, and delivers the completed EBSX file documents, the EBSX data file, and bid bond to KDOT using Bid Express.

Contractors wanting to bid as a prime contractor shall identify themselves below as a Bid Holder no later than the close of business on the Monday preceding the scheduled Letting Date. Contractors shall furnish this notice by clicking the "Bid Holders List" button contained in the Proposal Information for each Project on which the contractors intend to bid, complete the "Request Form" at the bottom and submit. This notice is necessary to obtain KDOT's approval to bid as a prime. In a few days please check the Bid Holder list to confirm KDOT's approval. Subcontractors, suppliers, and other interested entities may identify themselves below as a Non-bid Holder.


07/22/2020 Letting

Deadline for Bid Holders:   

 

Contract:  520072181Call #:  218
Project Number:  I435-046 KA-5632-01
Federal Project Number:  ACNHP-A563(201)
County:  JOHNSON
Project Work Description:  MILL, HMA OVERLAY AND PCCP PATCH.


Working Days:  30KDOT Construction Office:  OLATHE
Earliest Starting Date:  ***Latest Starting Date:  SEPTEMBER 14, 2020







If you would like to be added to one of the lists, Please click the appropriate button and then complete the submission form located at the bottom of this page.






Contract:  520072191Call #:  219
Project Number:  081 U 2361-01
Federal Project Number:  STP-C494(320)
County:  RILEY
Project Work Description:  GRADING & SURFACING


Working Days:  50KDOT Construction Office:  WAMEGO
Earliest Starting Date:  SEPTEMBER 14, 2020Latest Starting Date:  NOVEMBER 16, 2020







If you would like to be added to one of the lists, Please click the appropriate button and then complete the submission form located at the bottom of this page.






Contract:  520072262Call #:  226
Project Number:  I070-021 KA 3954-01
Federal Project Number:  NHPP-0704(094)
County:  DICKINSON
Project Work Description:  GRADING, BRIDGE AND SURFACING


Working Days:  CCDKDOT Construction Office:  JUNCTION CITY
Earliest Starting Date:  SEE SPECIAL PROVISIONLatest Starting Date:  SEE SPECIAL PROVISION







If you would like to be added to one of the lists, Please click the appropriate button and then complete the submission form located at the bottom of this page.






Contract:  520072272Call #:  227
Project Number:  K004-059 KA-5648-01
Federal Project Number:  ACSTP-A564(801)
County:  MCPHERSON
Project Work Description:  BRIDGE REPAIR


Working Days:  10KDOT Construction Office:  SALINA
Earliest Starting Date:  ***Latest Starting Date:  MAY 03, 2021







If you would like to be added to one of the lists, Please click the appropriate button and then complete the submission form located at the bottom of this page.






Contract:  520072363Call #:  236
Project Number:  084 C 4933-01
Federal Project Number:  HSIP-C493(301)
County:  RUSSELL
Project Work Description:  SIGNING


Working Days:  105KDOT Construction Office:  HAYS
Earliest Starting Date:  SEPTEMBER 08, 2020Latest Starting Date:  NOVEMBER 30, 2020







If you would like to be added to one of the lists, Please click the appropriate button and then complete the submission form located at the bottom of this page.






Contract:  520072464Call #:  246
Project Number:  U059-050 KA 5154-01
Federal Project Number:  ACSTP-A515(401)
County:  LABETTE
Project Work Description:  GRADING & SURFACING


Working Days:  80KDOT Construction Office:  PITTSBURG
Earliest Starting Date:  ***Latest Starting Date:  MARCH 01, 2021







If you would like to be added to one of the lists, Please click the appropriate button and then complete the submission form located at the bottom of this page.






Contract:  520072565Call #:  256
Project Number:  008 N 0685-01
Federal Project Number:  TA-N068(501)
County:  BUTLER
Project Work Description:  PEDESTRIAN & BICYCLE PATH


Working Days:  95KDOT Construction Office:  WICHITA-NORTH
Earliest Starting Date:  ***Latest Starting Date:  SEPTEMBER 14, 2020







If you would like to be added to one of the lists, Please click the appropriate button and then complete the submission form located at the bottom of this page.






Contract:  520072575Call #:  257
Project Number:  106 KA 4748-03
Federal Project Number:  HSIP-A043(318)
County:  RENO
Project Work Description:  SIGNING


Working Days:  75KDOT Construction Office:  HUTCHINSON
Earliest Starting Date:  ***Latest Starting Date:  MAY 03, 2021







If you would like to be added to one of the lists, Please click the appropriate button and then complete the submission form located at the bottom of this page.






Contract:  520074191Call #:  419
Project Number:  003 C 4959-01
Federal Project Number:  STP-C494(320)
County:  ATCHISON
Project Work Description:  GRADING & BRIDGE


Working Days:  90KDOT Construction Office:  HORTON
Earliest Starting Date:  ***Latest Starting Date:  MARCH 29, 2021







If you would like to be added to one of the lists, Please click the appropriate button and then complete the submission form located at the bottom of this page.






Contract:  520076131Call #:  613
Project Number:  106 KA 5620-01
Federal Project Number:  
County:  STATEWIDE
Project Work Description:  SIDEWALK IMPROVEMENTS


Working Days:  85KDOT Construction Office:  HORTON
Earliest Starting Date:  ***Latest Starting Date:  SEPTEMBER 28, 2020







If you would like to be added to one of the lists, Please click the appropriate button and then complete the submission form located at the bottom of this page.






Contract:  520076232Call #:  623
Project Number:  106 KA-5778-01
Federal Project Number:  
County:  STATEWIDE
Project Work Description:  MILLING RAP SAMPLE


Working Days:  10KDOT Construction Office:  BELLEVILLE
Earliest Starting Date:  ***Latest Starting Date:  AUGUST 20, 2020







If you would like to be added to one of the lists, Please click the appropriate button and then complete the submission form located at the bottom of this page.






Contract:  520076393Call #:  639
Project Number:  U024-071 KA-5539-01
Federal Project Number:  
County:  OSBORNE
Project Work Description:  GRADING


Working Days:  30KDOT Construction Office:  PHILLIPSBURG
Earliest Starting Date:  ***Latest Starting Date:  APRIL 05, 2021







If you would like to be added to one of the lists, Please click the appropriate button and then complete the submission form located at the bottom of this page.






Contract:  520076434Call #:  643
Project Number:  106 KA-5773-01
Federal Project Number:  
County:  STATEWIDE
Project Work Description:  MILLING RAP SAMPLE


Working Days:  5KDOT Construction Office:  IOLA
Earliest Starting Date:  ***Latest Starting Date:  OCTOBER 19, 2020







If you would like to be added to one of the lists, Please click the appropriate button and then complete the submission form located at the bottom of this page.






 

Total Records: 13



LEGEND

** THIS PROJECT IS GOVERNED BY THE LATEST VERSION OF SPECIAL PROVISION 15-01012 (SEASONAL LIMITATIONS (OVERLAYS))
*** As Soon as We Have a Valid Contract

 


Bid Holder or Non-Bid Holder List
Request Form

* Denotes a Required Field

Special Characters are not allowed in input.
Please refrain from using: # $ % ^ & , * : " ; ' < > ( ) / \ { } [ ]


*  

*  

*  

*  

*  

*  

*  
 

    


 


Questions or Comments may be sent to:
Lee Alvarado Lee.Alvarado@ks.gov, (785) 296-3576.

Back to Top